London 2012 Olympic Games – Professional Service
Home to 21,000 international Broadcasters and Press during the London 2012 Olympic Games, the International Broadcast Centre and Main Press Centre (IBC/MPC) were the hub for all press and broadcasting services with a global audience reaching 4 billion people.
How we helped our client:
- Managed a 400% scope/ budget increase and still achieved the original open date of 27 Jun 12 (first Olympic Park operational venue)
- Delivered G59 tests and generator sync on/off capability (34nr generators/ 34 Megawatts)
- Negotiated build over agreements with UK utility companies
- Managed all hard and soft FM services during Games time